Sattva Ekatra Construction Status
Sattva Ekatra construction status shows early layout work, with 12% overall progress in the update filed on 15 October 2026. Plot formation was at 25%. A combined civil-work group was at 20%. It covers roads, footpaths, drains and power poles.
The project covers 24.36 acres at Thippapura, Doddaballapura, with 502 residential plots. Power supply and tree planting were both at 0% in the same update. The site office and entrance are ready. Work on plot services is still in progress. The filed target to finish the project is 19 March 2029.