Sattva Ekatra Construction Status

Featured Image of Sattva Ekatra Construction Status


Sattva Ekatra construction status shows early layout work, with 12% overall progress in the update filed on 15 October 2026. Plot formation was at 25%. A combined civil-work group was at 20%. It covers roads, footpaths, drains and power poles.

The project covers 24.36 acres at Thippapura, Doddaballapura, with 502 residential plots. Power supply and tree planting were both at 0% in the same update. The site office and entrance are ready. Work on plot services is still in progress. The filed target to finish the project is 19 March 2029.

Sattva Ekatra Construction Status: October 2026


The Sattva Ekatra construction update lists progress by task. Each figure applies to the work named beside it. The overall figure covers the whole project. The table shows work done so far and tasks yet to start, based on the 15 October filing.

Work Item Progress in the 15 October Submission
Overall project progress 12%
Plot formation 25%
Roads, footpaths, drains and electrical poles: combined work group 20%
Power supply, transformer and substation 0%
Plantation 0%
Other miscellaneous work 3%

The separate roads entry is at 0%. The combined civil-work group is at 20%. It covers more than roads alone. The filing does not split that figure between drains, footpaths and poles. Use the roads entry when checking whether the internal roads are finished.

Current Site Progress in October 2026


The project site has a working marketing office with a paved forecourt, seating area and landscaped garden. The entrance gate is ready. Visitor parking is available. A Sattva-branded boundary wall has been placed along the approach road. Wayfinding signage is also available near the site.

Sattva Ekatra site progress covers this visitor setup and work inside the layout. Buyers can visit the site to see the office, entrance and approach road. At the chosen plot, look at the road, drains and service routes around it. These show how the work relates to that part of the site.

Plot Formation and Layout Work Status


Plot formation status was 25% in the October update. This stage covers work to shape and mark out the plots. The layout includes roads that are 9 metres and 12 metres wide. Plot work and road work have their own entries in the filed schedule.

The Sattva Ekatra development status shows power supply work at 0% in that report. This entry covers the transformer and substation. Work on power poles falls under a different group. The two entries do not show the same stage of work.

Sattva Ekatra RERA Status


Sattva Ekatra is RERA-approved under PR/180926/008945. The full registration number is PRM/KA/RERA/1250/301/PR/180926/008945. The layout is sanctioned by the Doddaballapur Planning Authority (DPA) under plan number DPA/TP/LAO/30/25-26.

The filed project start date is 1 October 2026. The work schedule sets out when each task is due to finish. Read those dates with the progress figures. The date a task is due and the amount of work done are two different details.

Site Progress Photos


Sattva Ekatra is located in Thippapura, Doddaballapura, North Bengaluru, Karnataka 562163. The RERA-filed coordinates for the site are 13.269251° N, 77.543884° E. Dated photos from this site help buyers follow work on the land and shared spaces.

RERA-Filed Site Photos — 22 May 2026

These GPS-stamped photos were filed with the Karnataka RERA application for Sattva Ekatra. They record the land at Thippapura before layout works began: cleared ground, the sheet-fenced boundary, the contractor cabin and the overhead power line along the site.

Cleared project land — 22 May 2026

Project land and boundary — 22 May 2026

Site office area — 22 May 2026

These images show the site in May 2026. Newer site progress photos show later work. Views of the same road, plot block or drain on different dates let buyers see what has changed. A capture date gives each photo a clear place in the work record.

Construction Timeline and Next Milestones


The next filed target is to finish plot formation by 28 February 2027. Tree planting is due to finish in June 2027. Power supply and combined civil works have later dates in the same year. These are planned dates in the work schedule.

Work Stage Filed Target Date
Plot formation 28 February 2027
Plantation 23 June 2027
Power supply work 11 October 2027
Combined road, footpath, drain and electrical-pole work 10 November 2027
Overall project completion 19 March 2029

The construction timeline gives each work group its own target. The next update should show how far each has moved from the October figures. The clubhouse and pool need their own work and opening dates. The road and power targets do not set those dates.

Sattva Ekatra Possession Date


The planned completion date is 19 March 2029. This is the target filed with RERA. The sale agreement sets out the date and terms for plot handover. Finishing the wider project and handing over a chosen plot are separate steps.

Buyers should track the timeline through RERA updates and site progress. Before planning to build, check the road, water, drains and power for the chosen plot. A single figure for the whole site does not show the services ready at each plot.

FAQs


1. What is the latest Sattva Ekatra construction status?

The update filed on 15 October 2026 reports 12% overall progress and 25% plot formation. Combined civil works were at 20%. Power supply and tree planting were both at 0%.

2. Has construction started at Sattva Ekatra in Doddaballapura?

Yes. The October record shows plot formation and combined civil works in progress. The project was in the early stages of layout work. The figures do not show that plots are ready to build on.

3. Are the internal roads complete?

The separate roads entry is at 0%. A combined group for roads, footpaths, drains and power poles is at 20%. It does not confirm finished roads.

4. Are the clubhouse and swimming pool ready?

The overall figure does not show whether either is ready to use. Ask for a dated update on these spaces and when they will open. Plot and road progress alone cannot confirm this.

5. When is project completion planned?

The filed target to finish the project is 19 March 2029. Plot work and services have earlier targets in the filed schedule. Check the handover date for the chosen plot in the sale agreement.