Sattva Ekatra RERA Approval

Featured Image of Sattva Ekatra RERA Approval


Sattva Ekatra RERA approval was approved on 18 September 2026 by the Karnatakara RERA under registration number PRM/KA/RERA/1250/301/PR/180926/008945. The registered promoter is Shirasa Construction Private Limited, a Sattva Group company. The project is at Thippapura, Doddaballapura, North Bengaluru.

DPA approved the layout on 17 July 2026 under plan DPA/TP/LAO/30/25-26. The site covers 24.36 acres, with 502 residential plots and one commercial plot in the filed schedule. The proposed completion date is 19 March 2029. The RERA certificate is valid till that date, unless renewed.

Sattva Ekatra Thippapura RERA Status and Registration Details


The Sattva Ekatra RERA status is registered. The site is filed as an ongoing plotted project. This gives buyers a record to check. It does not mean all work is done. Roads, power and shared spaces need their own dated work updates.

Record Field Filed Detail
Project name Sattva Ekatra
Full RERA number PRM/KA/RERA/1250/301/PR/180926/008945
Approval date 18 September 2026
Registered promoter Shirasa Construction Private Limited
Brand Sattva Group
Project type Plotted development
Land area 98,590 sq. metres, about 24.36 acres
Plot schedule 502 residential plots and one commercial plot
Planning authority Doddaballapur Planning Authority
Layout approval DPA/TP/LAO/30/25-26, dated 17 July 2026
Proposed completion 19 March 2029
Validity printed on certificate 19 March 2029, unless renewed

Use these Sattva Ekatra RERA details to check the papers for your plot. Match the name and number with the sale agreement. The civic amenity site has its own area on the plan. It is not the commercial plot or one of the 502 home plots.

Sattva Ekatra RERA Certificate


The Sattva Ekatra RERA certificate is a one-page PDF from the official state website. It names the project and company. It shows the grant date as 18 September 2026 and is valid till 19 March 2029, unless renewed. It has a QR code for checks too.

View the official RERA registration certificate — PDF

The ACK reference is ACK/KA/RERA/1250/301/PR/070926/010574, dated 7 September 2026. This marks the request for registration. It is not the granted RERA number. The codes show two steps. Use the issued number to check the project.

How to Verify Sattva Ekatra RERA Number


For Karnataka RERA project verification, use the official portal. Search for SATTVA EKATRA and match the full number. The company, address and site area must agree with the file. Then check the plan and papers for your chosen plot.

  • Find the project by its filed name and full RERA number.
  • Match the company and Thippapura address with the official PDF.
  • Open the sanctioned layout plan and plot list.
  • Check the chosen plot’s number, area and boundaries.
  • Check dated work updates and any later orders that change the end date.

A brochure shows the wider layout. The plot list gives the area and boundaries of each site. Match your plot with the sale agreement too. Save the plan and papers so you can refer to the same records at each step.

Sattva Ekatra DPA Approval: DPA or BIAAPA?


The layout is approved by the Doddaballapur Planning Authority. The Sattva Ekatra layout approval number is DPA/TP/LAO/30/25-26, dated 17 July 2026. DPA approves the plan; Karnataka RERA registers the project. Match both records to the same site and company.

DPA was set up on 20 March 2018. State records describe a planning area formed from 257 villages taken from BIAAPA and 37 from Nelamangala Planning Authority. DPA is the authority named in this project’s file. A shared PIN code is not proof of BIAAPA approval.

Sattva Ekatra Doddaballapura: Registered Land Details


The registered plotted layout covers 11 survey numbers. These mark the land on file at Thippapura Village, Kasaba Hobli. Match the numbers below with the title papers and plan. The area, village and plot must be the same in each file.

Survey numbers: 42, 43/1, 43/2, 44/1, 44/3, 45/1, 45/2, 46/1, 46/2, 46/3 and 47/1.

OS No. 503/2023 appears in the land file. It concerns Survey No. 45/1, measuring 1 acre 35 guntas. A lawyer should review the current case status, court orders and their effect on the chosen plot. A RERA number alone does not settle a land dispute.

RERA Completion Date and Project Updates


The Sattva Ekatra RERA registration records a start date of 1 October 2026. The planned finish date is 19 March 2029. The official PDF is valid till 19 March 2029, unless renewed. Read any later order with these dates.

Quarterly updates show work done against the plan. Keep the date with each figure. Roads, power, parks and shared spaces may be at different stages. The overall figure does not set the plot handover date or show when the clubhouse and pool will open.

Documents and Payment Checks Before Booking


Check the RERA PDF, DPA plan, title and ownership papers, plot list and sale agreement. The plot number, area and boundaries must match. Have a lawyer read the suit and court orders before you sign. The written terms should also state the payment dates and refund rules.

For an advance or application fee above 10% of the plot cost, a written agreement for sale must first be signed and registered. This is the rule under Section 13 of the RERA Act. Check the project bank account before paying. Keep the receipt with the plot papers.

FAQs


1. Is Sattva Ekatra RERA approved?

Yes. The official PDF records the grant on 18 September 2026. Its number and company are in the table above. Match them with your plot papers.

2. When was the project registered?

The grant date is 18 September 2026. The earlier ACK reference is dated 7 September 2026. One is for the request. The other is for the issued RERA number.

3. Can I download the Sattva Ekatra RERA certificate?

Yes. Open the official PDF and save it. Check the name and number. Then check the address, company and end date. Read any later orders with the first PDF.

4. Does RERA registration guarantee a clear land title?

It does not replace a title check. The land file lists a suit about Survey No. 45/1. A lawyer should review the case and any orders that affect the land.

5. Is 19 March 2029 the confirmed possession date?

It is the planned finish date on file and the end date printed on the RERA PDF. The sale agreement should state the exact date and terms for plot handover.