Sattva Ekatra Project Schedule

Featured Image of Sattva Ekatra Project Schedule


The Sattva Ekatra project schedule starts on 1 October 2026 and proposes completion on 19 March 2029. The 24.36-acre layout is at Thippapura, Doddaballapura. It includes 502 residential plots and one commercial plot.

Plot formation is targeted for 28 February 2027. Planting is due to finish by 23 June 2027. Power supply work has a finish target of 11 October 2027. Combined work on roads, footpaths, drains and power poles has a target of 10 November 2027. Other miscellaneous work runs through 19 March 2029.

Sattva Ekatra Project Schedule and Work Dates


The Sattva Ekatra development timeline lists five work groups. Each has a planned start and finish date. Several tasks overlap. Roads, planting and power work can therefore run at the same time. The table gives the work periods filed with Karnataka RERA.

Work Stage Estimated Start Target Finish
Plot formation 1 October 2026 28 February 2027
Roads, footpaths, drainage and electrical poles: combined work group 13 February 2027 10 November 2027
Power supply, transformer and substation 4 April 2027 11 October 2027
Plantation 23 February 2027 23 June 2027
Other miscellaneous work 1 October 2026 19 March 2029

This layout work schedule gives planned dates. It is filed for the project under RERA number PRM/KA/RERA/1250/301/PR/180926/008945. Use dated progress reports to see work done so far. Check for any later changes to the plan too.

Plot Formation Schedule


The Sattva Ekatra plot formation schedule runs from 1 October 2026 to 28 February 2027. This is the first main work group in the filed plan. It covers forming the plots within the site. Building a private house on a plot is a separate task.

The five standard plot sizes range from 600 to 1,800 sq. ft. There are also 139 odd-size plots. Plot formation alone does not make roads, water and power ready at each plot. These services need their own progress checks.

Road, Footpath and Drainage Work


The combined civil-work period runs from 13 February to 10 November 2027. It groups roads, footpaths, drains and power poles. The layout has 9-metre and 12-metre roads. The filing gives one finish date for this work group, not a date for each item.

Road-related work is due to start before plot formation ends on 28 February 2027. The two groups overlap in February. Parts of the layout can move ahead at different rates, rather than all plots reaching the same stage together.

Power Supply and Plantation Dates


The power supply schedule runs from 4 April to 11 October 2027. It covers the transformer and substation work group. Power poles fall under the civil-work group instead. Work on poles alone does not show that the power supply is ready.

Plantation is scheduled from 23 February to 23 June 2027. This period overlaps with plot formation, roads and power work. The plan allows planting while other work is still in progress. It does not leave all planting until the end of the build period.

Overall Completion and Plot Handover


The Sattva Ekatra completion timeline has a target of 19 March 2029. Other miscellaneous work has the same end date. The filing does not list each task within that group. It therefore gives no separate opening date for the clubhouse or pool.

The 2027 targets for roads, power and planting fall before the full project finish date. They do not confirm plot handover in 2027. The sale agreement should state the exact handover date and terms. Plot services and required approvals need to be in place too.

How to Track Development Milestones


Use the work schedule to see what is due. Use dated updates to see what has been done. A planned start date does not prove work began that day. The same applies to a target finish date.

At the site, view the chosen plot, its approach road, drains and service routes. Keep the date with each report and photo. This helps buyers follow the Sattva Ekatra construction milestones and match the filed dates with work on the ground.

FAQs


1. How long is the planned project period?

The filed period runs from 1 October 2026 to 19 March 2029, or about 29 months. It covers work on the layout. A private house has its own build plan and timing.

2. When should plot formation finish?

The filed target is 28 February 2027. Road-related work is due to start on 13 February 2027. The two groups overlap; use dated work updates to check actual progress.

3. Does the November 2027 road target mean the project is complete?

No. That work group is due to finish on 10 November 2027. The whole project has a filed target of 19 March 2029. Other work runs until then.

4. Is 19 March 2029 the confirmed possession date?

It is the filed proposed completion date. The sale agreement should state the exact plot handover date, services and conditions. The planned finish date alone does not confirm possession.